打ち上げ後の運用スケジュール

打上から一週間分の運用の流れは次のとおりです.

大まかには,通信系の確立や電源の電力収支の確認を行って参ります.通信に関しては,最初にCWを行います.その後FMダウンリンクのテストを行います.電源系は電圧値の読み取り等を行います.TLEが発行されるまでは,軌道決定も随時行ってまいります.

以下に,最新のTLEと日にち毎の運用の予定を示します.

 In a week from the SPLOUT launch, we will do following operation.

Generally speaking, we will establish communication system in SPROUT and check electronic power supply system. In communication system, at first, we will use CW. After that, we will test about FM downlink. In electronic power supply system, we will read voltage value and so on. Until NORAD issue TLE, we will also do orbit determination at any time.

I show you the latest TLE and list of operation.

 

TLE: SPROUT
1 00000U 14001A 14144.15446759 .00000000 00000-0 00000-0 0 0013
2 00000 97.8740 241.6718 0035980 58.6810 194.6458 14.85960816 14
(Latest:2014/05/24/13:10)
 

1日目1stパス(13:44:04~,7分間程度):データ送受信確立と確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.アップリンクの確認

5.ビーコン電波測定に基づく軌道決定

 

1日目2nd~3rdパス:システム健全性確認→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.アップリンクの確認

5.ビーコン電波測定に基づく軌道決定

 

2日目1stパス:システム健全性確認→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.アップリンクの確認

5.ビーコン電波測定に基づく軌道決定

 

2日目2nd~6thパス:電力収支の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.ビーコン電波測定に基づく軌道決定

 

3日目1st~5thパス:電力収支の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.ビーコン電波測定に基づく軌道決定

 

4日目1st~2ndパス:電力収支の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.ビーコン電波測定に基づく軌道決定

 

4日目3rdパス:データ送受信確率と確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.1200bpsFMダウンリンクの確認

5.ビーコン電波測定に基づく軌道決定

 

4日目4thパス:電力収支の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.ビーコン電波測定に基づく軌道決定

 

4日目5thパス:電力収支,システム健全性の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.1200bpsFMダウンリンクの確認

5.ビーコン電波測定に基づく軌道決定

 

5日目1stパス:電力収支の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.ビーコン電波測定に基づく軌道決定

 

5日目2ndパス:電力収支,システム健全性の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.1200bpsFMダウンリンクの確認

5.ビーコン電波測定に基づく軌道決定

 

5日目3rdパス:電力収支の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.ビーコン電波測定に基づく軌道決定

 

5日目4thパス:電力収支,システム健全性の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.1200bpsFMダウンリンクの確認

5.ビーコン電波測定に基づく軌道決定

 

6日目1stパス:電力収支,システム健全性の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.1200bpsFMダウンリンクの確認

5.ビーコン電波測定に基づく軌道決定

 

6日目2ndパス:データ送受信確立の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.ビーコン電波測定に基づく軌道決定

 

6日目3rdパス:データ送受信確立の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.1200bpsFMダウンリンクの確認

5.ビーコン電波測定に基づく軌道決定

 

6日目4thパス:データ送受信確立の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.ビーコン電波測定に基づく軌道決定

 

7日目1st~2ndパス:データ送受信確立の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.1200bpsFMダウンリンクの確認

5.ビーコン電波測定に基づく軌道決定

 

7日目3rdパス:データ送受信確立の確認

→1.テレメトリ開始確認

2.CWビーコン電波受信

3.テレメトリデータの確認

4.ビーコン電波測定に基づく軌道決定

 

 

・1st path in 1st day (13:44:04~, about 7 min.): establish and check communication.

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. check the up-link.

5. determine orbit by the observation of beacon.

 

・2nd to 3rd path in 1st day: check of system’s soundness.

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. check the up-link.

5. determine orbit by the observation of beacon.

 

・1st path in 2nd day: check of system’s soundness.

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. check the up-link.

5. determine orbit by the observation of beacon.

 

・From 2nd to 6th path in 2nd day: check electronic power supply systems.

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. determine orbit by the observation of beacon.

 

・From 1st to 5th path in 3rd day: check electronic power supply systems.

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. determine orbit by the observation of beacon.

 

・1st and 2nd path in 4th day: check electronic power supply systems.

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. determine orbit by the observation of beacon.

 

・3rd path in 4th day: establish and check communication

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. check downlink of FM 1200bps

5. determine orbit by the observation of beacon.

 

・4th path in 4th day: check electronic power supply systems.

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. determine orbit by the observation of beacon.

 

・5th path in 4th day: check electronic power supply system and system’s soundness

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. check downlink of FM 1200bps

5. determine orbit by the observation of beacon.

 

・1st path in 5th day: check electronic power supply systems.

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. determine orbit by the observation of beacon.

 

・2nd path in 5th day: check electronic power supply system and system’s soundness

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. check downlink of FM 1200bps

5. determine orbit by the observation of beacon.

 

・3rd path in 5th day: check electronic power supply systems.

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. determine orbit by the observation of beacon.

 

・4th path in 5th day: check electronic power supply system and system’s soundness

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. check downlink of FM 1200bps

5. determine orbit by the observation of beacon.

 

・1st path in 6th day: check electronic power supply system and system’s soundness

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. check downlink of FM 1200bps

5. determine orbit by the observation of beacon.

 

・2nd path in 6th day: check establishment of data communication

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. determine orbit by the observation of beacon.

 

・3rd path in 6th day: check establishment of data communication

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. check downlink of FM 1200bps

5. determine orbit by the observation of beacon.

 

・4th path in 6th day: check establishment of data communication

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. determine orbit by the observation of beacon.

 

・1st to 3rd path in 7th day: check establishment of data communication

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. check downlink of FM 1200bps

5. determine orbit by the observation of beacon.

 

・4th to 6th path in 7th day: check establishment of data communication

→1.check the starting telemetry.

2. receive beacon of CW.

3. check the telemetry data.

4. determine orbit by the observation of beacon.